| Construction of CHP on the base of gas-pumped installation for energy supply of aluminum dishware plant in Stupino. Station power: electric – 1,5 MWt, heat – 2,7 MWt.  Technical performance: Temporary energy supply (prior to factory launch) - Volvo engine-based diesel generators.
Constant energy supply - mini CHP on the base of gas-pumped installation (FG Willson design).  Economical parameters: Total project costs: $2.1 Mil. Loan/equity proportion:  50/50.
Equity = $1,05 Mil. |